Week of October 10: Reach 3A Project Update - October 11, 2016
Note: these timelines are estimates from T&S Construction and are subject to change.
October 10-14: Crews will be working on pipeline replacement behind the Moose Lodge. They will also be testing pipelines between the Lodge and Blagen Road. This will impact activities at the Lodge and cause minor traffic delays, as heavy construction equipment will be moving back and forth in the area. Crews will also be working on a creek crossing near Dr. Arnold’s office. Crews will also begin work on a creek crossing near the Black Bear Inn on October 14. Finally, construction crews will be working on various projects in the old Meadowmont Golf Course throughout the week.
October 17-21: Crews are expected to finish testing pipelines in the area of the Moose Lodge by Oct. 19. They are also planning to continue on the creek crossing at the Black Bear Inn on Oct. 17 and 18. A hydrant will be installed on D Street on October 17 and 18. Paving will be done on Blagen Road between October 18 and 21.
October 24-28: Crews will be trenching and replacing pipe between the Meadowmont Shopping Center and Snowshoe Brewery. They will also be working on the completion of the creek crossing near the Black Bear Inn.
If you have questions or concerns about the project, contact CCWD at (209) 754-3543 or email customerservice@ccwd.org