Reach 3A Project Update: July 24 – August 11July 24, 2017

Construction Update

July 24-28: Construction crews will complete the tie-in of a new section of pipeline into the main water distribution system on Blagen Road, which could cause minor traffic delays in the area on Monday July 24. On July 25, crews will begin trenching and installation of new pipeline near the cabinet shop at the corner of Willow Street and Sequoia Road heading toward Cedar Center.

July 31 – August 4:  Crews are expected to complete trenching from the cabinet shop to the edge of Cedar Center by Monday July 31. Starting on August 1,  crews will be trenching and installing new pipeline through Cedar Center. Large equipment and construction activity will create traffic delays in the area, and some businesses will be impacted by this work. CCWD is notifying businesses in the area of this upcoming work.

August 7-11

Crews will continue trenching and installation of new pipeline through Cedar Center. Large equipment and construction activity will continue to create traffic delays in the area, and some businesses will be impacted by this work.

Project summary

As of July, T&S Construction had replaced about 16,000 feet of pipeline and another 3,000 feet remain, and the project is about 85 percent finished. The remaining portions of pipeline that need to be replaced are from Pine Drive through Oak Court and Cedar Center to Sequoia Street. Substantial completion of the project is expected in August 2017.