Reach 3A Project Update: August 7 – 18

Construction Update   August 7-11 Crews will continue trenching and installation of new pipeline through Cedar Center and along Oak Court. Large equipment and construction activity will continue to create traffic delays in the area, and access to businesses and parking will be impacted by this work. August 13-18 Once new pipeline has been installed…

Reach 3A Project Update: April 21-May 5

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and…

Reach 3A Project Update: Week of April 3

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21…

Some Arnold Customers May Experience Low Water Pressure Tonight

Some CCWD customers in Arnold may experience low water pressure tonight (January 18) through tomorrow morning (January 19), due to work on an ongoing emergency water transmission line construction project. This project was initially expected to be complete by 10 p.m. January 18, but poor weather conditions created challenging working conditions. CCWD now expects to…

CCWD Crews Stabilize Arnold Water Transmission Line

Update at 11 a.m. Thursday Jan. 12: CCWD Crews worked with T&S Construction throughout the night Wednesday to stabilize the exposed water transmission pipeline that provides Arnold’s main water supply. A metal I-beam was placed across the washed-out section of Blagen Road directly over the exposed pipeline, and heavy duty straps were wrapped from the beam to the pipeline…