Reach 3A Project Nears Completion: Update August 16 – Sept. 15

The Reach 3A Pipeline Replacement Project in Arnold is nearing completion. One 500-foot section of old pipeline remains between Oak Court and Pine Drive near the Black Bear Inn. During the final phase of construction, heavy equipment and construction activities will cause traffic delays and create noise in the area between 7 a.m. and 3:30…

Planned Water Outage in Arnold, Monday April 3

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project.…

Reach 3A Project Update: December 21

Due to the winter storms that have been passing through the Arnold area, T&S Construction’s work schedule has been limited on the Reach 3A Project. Please see the construction schedule below for the planned construction schedule between December 22 and January 5. December 22: Construction crews will be performing work along Blagen Road near the entryway…

November 17: Reach 3A Project Update

Construction generally begins by 7 a.m. and crews head home by 3:30 p.m. Nov. 17 and 18: Contractors will be trenching and installing pipe between Snowshoe Brewery and the Meadowmont Shopping Center. Expect minor traffic delays. Nov. 21-23: Contractors will be testing the new pipeline between the Meadowmont Shopping Center and Pine Drive. Crews will…

August 5: Reach 3A Project Update

After several weeks of work, T&S Construction has completed its work on the Blagen Road section of the Reach 3A Pipeline Replacement Project. Crews performed final clean-up on Friday, August 5, in preparation for the Annual Flea Market at Independence Hall, which will be held on Saturday, August 6. CCWD thanks community members for their…