Reach 3A Project Update: April 26 – May 12

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection…

Reach 3A Project Update: April 21-May 5

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and…

Planned Water Outage in Arnold, Monday April 3

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project.…

August 5: Reach 3A Project Update

After several weeks of work, T&S Construction has completed its work on the Blagen Road section of the Reach 3A Pipeline Replacement Project. Crews performed final clean-up on Friday, August 5, in preparation for the Annual Flea Market at Independence Hall, which will be held on Saturday, August 6. CCWD thanks community members for their…