Reach 3A Pipeline Replacement Community Meeting

April 26, 2016 @ 6:00 pm - 7:00 pm

The Calaveras County Water District is holding a community meeting from 6 to 7 p.m. Tuesday April 26 to provide residents with information regarding the Reach 3A Transmission Pipeline Replacement Project. Construction will begin in May and the project is expected to be complete in November.

This project will replace about 20,000 feet of 12-inch diameter transmission pipeline that runs from the Arnold Cal-Fire Station along Highway 4 to Blagen Road and terminates at CCWD’s sawmill tank above White Pines.

Funding for this project comes from a combination of a $1.378 million grant from the United States Department of Agriculture, a $2.622 million loan from USDA and $1.3 million in local matching funds from CCWD’s Capital Renovation and Replacement fund. Construction will begin in May and the project is expected to be complete in November.

On April 26, CCWD staff will make a presentation that overviews the project and its impacts on the community along with taking questions from attendees.

CCWD staff planning to attend:

  • Dave Eggerton, General Manager
  • Charles Palmer, District Engineer
  • Jesse Hampton, Plant Operations Manager
  • Joel Metzger, Public Information Officer | Customer Relations Manager

Other attendees:

  • Bertha Underhill, District 3 CCWD Director
  • Representatives from T.S. Construction

 

For more information about this event, please call (209) 754-3123 or email joelm@ccwd.org

Details

Date:
April 26, 2016
Time:
6:00 pm - 7:00 pm
Event Categories:
,
Event Tags:
, , , , , , ,

Organizer

Venue

Typically, the Board of Directors meets on
the second and fourth Wednesdays of each month
Meetings begin at 9:00 a.m. between November February and 1 p.m. between March and October.

The public is invited and encouraged to attend.

The Board room is at District headquarters
120 Toma Court in San Andreas.

Subscribe to Receive Board Agendas

Menu