Water Service Restored to Meadowmont Subdivision

As of 1 p.m. Thursday, water service was restored to CCWD customers in the Meadowmont Subdivision in Arnold. The planned outage allowed contractors to install a valve on the water transmission pipeline they are replacing. The District thanks customers for their patience during the water outage. Click here to learn more about the Reach 3A Pipeline Replacement Project.…

Planned Water Outage in Meadowmont this Morning

Due to construction work on the Reach 3A Main Pipeline Replacement Project, about half of the Meadowmont Subdivision will experience a water outage from 7:30 a.m. to 3:30 p.m. today. For details about what homes will be affected by this outage, click here. Click here to learn more about the Reach 3A Pipeline Replacement Project. If…

Planned Water Outage in Meadowmont Subdivision September 8

Due to ongoing pipeline replacement construction work, a planned water outage will affect CCWD customers in a large portion of the Meadowmont Subdivision in Arnold from 7:30 a.m. to 3:30 p.m. Thursday September 8. District staff members have placed road signs throughout the area to alert residents of the date and time of the upcoming service disruption. Customers who…

August 22 – September 2: Reach 3A Project Update

Customers who live on Pine Drive in the Meadowmont Subdivision may experience a short water service disruption during the week of August 22nd or the week of August 29th. Signage placed on the street will notify customers of the exact dates and times of the outage once the plan is finalized. Contractors will be working on trenching and replacing…

August 5: Reach 3A Project Update

After several weeks of work, T&S Construction has completed its work on the Blagen Road section of the Reach 3A Pipeline Replacement Project. Crews performed final clean-up on Friday, August 5, in preparation for the Annual Flea Market at Independence Hall, which will be held on Saturday, August 6. CCWD thanks community members for their…

Construction Closures on Blagen Road Through August 5

Due to the Reach 3A Pipeline Replacement Project, Blagen Road will be closed to through traffic from 7 a.m. to 5:30 p.m. on weekdays from Tuesday, July 12 through Friday, August 5. CCWD’s contractor, T&S Construction, will be trenching to install pipeline infrastructure during this time. Motorists should use Dunbar Road as a detour to get around…

June 29: Reach 3A Project Update

Construction crews have begun work on Blagen Road and will be saw-cutting the asphalt and trenching moving from east to west, which will cause one-way traffic control. Dump trucks will be unloading soil from the trenching in the parking lot near Courtright-Emerson Memorial Ball Park, so residents in the area should keep an eye out for trucks and…

Water Service Restored to Arnold Customers

Water service has been restored to about 20 customers impacted by a scheduled water shutdown that took place between 7 a.m. and 5 p.m. Tuesday June 28 in Arnold. This shutdown allowed CCWD’s contractor – T&S Construction – to install isolation valves on the southwest end of town. This shutdown was part of the Reach 3A Water Transmission Line Replacement Project…

Water Shutdown Scheduled in Arnold Tuesday June 28

About 20 customers will be impacted by a scheduled water shutdown that will take place between 7 a.m. to 3 p.m. Tuesday June 28 in Arnold. This shutdown will allow CCWD’s contractor – T&S Construction – to install isolation valves on the southwest end of town. This shutdown is part of the Reach 3A Water Transmission Line Replacement Project…