CCWD Holds Reach 1 Project Town Hall Meeting

The Calaveras County Water District held a town hall meeting on Wednesday June 5 at Mountain Christian Fellowship near Forest Meadows to provide an overview of the Reach 1 Pipeline Replacement Project. Click here to view the PowerPoint Presentation. Click here for detailed information about the Reach 1 Pipeline Replacement Project. For more information, contact…

CCWD Joined by Community to Celebrate Completion of Reach 3A Project

More than 60 people joined the Calaveras County Water District Board of Directors and staff at Cedar Center in Arnold Wednesday for a ribbon-cutting ceremony to celebrate the completion of the $5.3 million Reach 3A Water Transmission Pipeline Replacement Project, which has been under construction since spring 2016. To kick off the ceremony, CCWD General…

Reach 3A Project Nears Completion: Update August 16 – Sept. 15

The Reach 3A Pipeline Replacement Project in Arnold is nearing completion. One 500-foot section of old pipeline remains between Oak Court and Pine Drive near the Black Bear Inn. During the final phase of construction, heavy equipment and construction activities will cause traffic delays and create noise in the area between 7 a.m. and 3:30…

Reach 3A Project Update: August 7 – 18

Construction Update   August 7-11 Crews will continue trenching and installation of new pipeline through Cedar Center and along Oak Court. Large equipment and construction activity will continue to create traffic delays in the area, and access to businesses and parking will be impacted by this work. August 13-18 Once new pipeline has been installed…

Reach 3A Project Update: April 21-May 5

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and…

Reach 3A Project Update: Week of April 3

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21…

Planned Water Outage in Arnold, Monday April 3

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project.…