Construction schedule: May 11 – 19 May 11-12: Crews will be digging a trench and installing sections of 12-inch ductile iron pipe along Sequoia Road heading east across Manuel Road and along Fir Street toward Dunbar Road. This work will cause traffic delays and heavy construction equipment will be moving in and out of the area. There will …

Read more

After nearly three months of work, Calaveras County Water District distribution crews have finished flushing the entire water system serving the greater Valley Springs area. Over the course of the effort, CCWD crews used 174 hydrants to flush more than 400,000 feet of pipe, or about 78 miles. The District thanks customers for their patience and …

Read more

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and …

Read more

Proposed flushing schedule for the week of April 17 (this schedule is subject to change): From Kirby Street heading south in Rancho Calaveras Mother Lode Acres Town of Jenny Lind General Flushing information The Calaveras County Water District is in the process of flushing its entire water distribution system in the greater Valley Springs area. …

Read more

Proposed flushing schedule for the week of April 10 (this schedule is subject to change): South end of Rancho Calaveras Mother Lode Acres Town of Jenny Lind   General Flushing information The Calaveras County Water District is in the process of flushing its entire water distribution system in the greater Valley Springs area. These operations …

Read more

Update 2:30 p.m.: Water Service has been restored to customers in Copperopolis. As of 1 p.m. Thursday, Calaveras County Water District crews were working to repair a water leak on Feather Drive in Copperopolis. This leak has caused residents who live on Feather Drive and in Sequoia, Morado or Iriquois Circles to experience a disruption in …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21 …

Read more

Due to a large number of leaks that must be repaired in greater Valley Springs area, flushing operations will be intermittent this week. Proposed flushing schedule for the week of April 4 (this schedule is subject to change): South end of Rancho Calaveras Mother Lode Acres Town of Jenny Lind Flushing information The Calaveras County …

Read more
Water Outage Flyer

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project. …