Reach 3A Project Update: April 26 – May 12

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection…

Reach 3A Project Update: April 21-May 5

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and…

Reach 3A Project Update: Week of April 3

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21…

Planned Water Outage in Arnold, Monday April 3

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project.…

CCWD Board Approves Mokelumne River Studies

On Wednesday January 25, the Calaveras County Water District Board of Directors unanimously authorized two studies involving the Mokelumne River in Calaveras County. Peter Martin, CCWD water resources program manager, explained one study will evaluate the specific water supply reliability and infrastructure needs of the West Point community, and the other will study the long-term…

Reach 3A Project Update: December 21

Due to the winter storms that have been passing through the Arnold area, T&S Construction’s work schedule has been limited on the Reach 3A Project. Please see the construction schedule below for the planned construction schedule between December 22 and January 5. December 22: Construction crews will be performing work along Blagen Road near the entryway…