Reach 3A Project Update: May 23 – June 9
Construction schedule: May 11 – June 9 May 22-25 – Crews will be installing ductile iron pipe on Fir Street heading northeast between Manuel Drive and Dunbar Road. Two pressure-reducing valves will be tied into the new system, and crews will pressurize and test the new section of pipeline. Residents should expect minor traffic delays…