Update September 28, 2017: CCWD crews paved Manuel and Sequoia Roads this afternoon. Tomorrow, crews will be paving in the Meadowmont Shopping Center parking lot, Cedar Center and Pine Drive. Next week, crews will pave around the entry to Snowshoe Brewery and on Meadowview Drive. All paving is expected to be complete by the end …

Read more

There will be a planned water outage from 9 a.m. to noon Friday June 23 in Arnold. This service disruption will impact all residential CCWD customers on Fir Street, Dunbar Road and Linebaugh Road. It will also impact Ebbetts Pass Gas, Chevron and Arnold Ace Home Center. Those with questions or concerns about this planned water …

Read more

Construction Schedule June 14-June 16: Crews will be trenching and installing 12-inch ductile iron piping along Dunbar Road. They will also tie in a pressure-reducing valve at the corner of Dunbar and Blagen Roads. Traffic control will be in effect during this work. Once the new section of piping is installed, they will begin testing. …

Read more

Construction Schedule May 30-June 2: Crews will be testing recently installed pipeline along Fir Street. This work may require minor traffic delays. June 5-9: Crews will be connecting a pressure-reducing valve to the water distribution system along Fir Street. They will also be installing ductile iron piping along Dunbar Road between its intersection with Fir …

Read more

Construction schedule: May 11 – June 9   May 22-25 – Crews will be installing ductile iron pipe on Fir Street heading northeast between Manuel Drive and Dunbar Road. Two pressure-reducing valves will be tied into the new system, and crews will pressurize and test the new section of pipeline. Residents should expect minor traffic delays …

Read more

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and …

Read more

As of 1:30 p.m. Monday April 3, water service was restored to businesses and homes in the Arnold area. Service was temporarily disrupted starting at 8 a.m. Monday to allow for a waterline tie-in, which is part of the ongoing Reach 3A Pipeline Replacement Project (see initial post about the planned outage here). After constructions …

Read more
Water Outage Flyer

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project. …

Read more

After several weeks of work, T&S Construction has completed its work on the Blagen Road section of the Reach 3A Pipeline Replacement Project. Crews performed final clean-up on Friday, August 5, in preparation for the Annual Flea Market at Independence Hall, which will be held on Saturday, August 6. CCWD thanks community members for their …

Read more