The Calaveras County Water District is in the design process of a project that will replace and upgrade sewer infrastructure in communities around Lake Tulloch in Copperopolis. For details about this project, click here. The District is committed to keeping the communities in and around the project area updated on planning and construction activities, and regular posts will be made on the District’s website and social media accounts. An email list has also been developed, where the latest information will be sent directly to community members (to be added to this list, please contact Joel at joelm@ccwd.org).

Project update: October 23 – Nov. 1

O’Dell Engineering is scheduled to start surveying work on Tuesday October 24. They will be working for a week at the following locations:

  • Lake Tulloch Shores
    • 477 Bret Harte Drive
    • 608 Bret Harte Drive
    • 231 Poker Flat Road
  • Connor Estates
    • Boat storage parking lot area
  • Copper Cove
    • 5288 Lakeshore Drive
    • 4578 Kiva Drive (Kiva Park)
    • 4698 Kiva Drive
    • 4600 Kiva Drive

For more information about the Lake Tulloch Area Sewer Upgrades Project, contact Joel Metzger at joelm@ccwd.org, 209-754-3123 (Desk) or 209-768-6270 (Mobile).

Written by Joel Metzger