Reach 3A Project

Home » Reach 3A Project

Construction Schedule May 30-June 2: Crews will be testing recently installed pipeline along Fir Street. This work may require minor traffic delays. June 5-9: Crews will be connecting a pressure-reducing valve to the water distribution system along Fir Street. They will also be installing ductile iron piping along Dunbar Road between its intersection with Fir …

Read more

Construction schedule: May 11 – June 9   May 22-25 – Crews will be installing ductile iron pipe on Fir Street heading northeast between Manuel Drive and Dunbar Road. Two pressure-reducing valves will be tied into the new system, and crews will pressurize and test the new section of pipeline. Residents should expect minor traffic delays …

Read more

Construction schedule: May 11 – 19 May 11-12: Crews will be digging a trench and installing sections of 12-inch ductile iron pipe along Sequoia Road heading east across Manuel Road and along Fir Street toward Dunbar Road. This work will cause traffic delays and heavy construction equipment will be moving in and out of the area. There will …

Read more

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21 …

Read more
Water Outage Flyer

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project. …

Read more

Due to significant snowfall in the Arnold area, construction on the Reach 3A Project is on hold until further notice. CCWD’s contractor, T&S Construction, has replaced about 15,000 feet of pipeline since the project began and the project is more than 80 percent finished. The remaining portions of pipeline that need to be replaced are …

Read more

On Wednesday January 25, the Calaveras County Water District Board of Directors unanimously authorized two studies involving the Mokelumne River in Calaveras County. Peter Martin, CCWD water resources program manager, explained one study will evaluate the specific water supply reliability and infrastructure needs of the West Point community, and the other will study the long-term …

Read more

Due to the winter storms that have been passing through the Arnold area, T&S Construction’s work schedule has been limited on the Reach 3A Project. Please see the construction schedule below for the planned construction schedule between December 22 and January 5. December 22: Construction crews will be performing work along Blagen Road near the entryway …

Read more