Water Capital Improvements

Home » Water Capital Improvements

There will be a planned water outage from 9 a.m. to noon Friday June 23 in Arnold. This service disruption will impact all residential CCWD customers on Fir Street, Dunbar Road and Linebaugh Road. It will also impact Ebbetts Pass Gas, Chevron and Arnold Ace Home Center. Those with questions or concerns about this planned water …

Read more

Construction Schedule June 14-June 16: Crews will be trenching and installing 12-inch ductile iron piping along Dunbar Road. They will also tie in a pressure-reducing valve at the corner of Dunbar and Blagen Roads. Traffic control will be in effect during this work. Once the new section of piping is installed, they will begin testing. …

Read more

Construction Schedule May 30-June 2: Crews will be testing recently installed pipeline along Fir Street. This work may require minor traffic delays. June 5-9: Crews will be connecting a pressure-reducing valve to the water distribution system along Fir Street. They will also be installing ductile iron piping along Dunbar Road between its intersection with Fir …

Read more

Construction schedule: May 11 – June 9   May 22-25 – Crews will be installing ductile iron pipe on Fir Street heading northeast between Manuel Drive and Dunbar Road. Two pressure-reducing valves will be tied into the new system, and crews will pressurize and test the new section of pipeline. Residents should expect minor traffic delays …

Read more

Thousands of feet of aging water distribution pipeline will be replaced this summer as part of a construction project the Calaveras County Water District (CCWD) is launching in Rancho Calaveras. All construction work is being performed in-house by CCWD construction and distribution crews. The first phase of the project is on Harper Street, where crews …

Read more

Construction schedule: May 11 – 19 May 11-12: Crews will be digging a trench and installing sections of 12-inch ductile iron pipe along Sequoia Road heading east across Manuel Road and along Fir Street toward Dunbar Road. This work will cause traffic delays and heavy construction equipment will be moving in and out of the area. There will …

Read more

Due to improved weather conditions, CCWD’s contractor (T&S Construction) has resumed work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. This is the proposed construction schedule for the next two weeks (schedule is subject to change). Construction schedule: April 26 – May 12 April 26-28: At the intersection …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next two weeks (this schedule is subject to change). Construction update: April 21-May 5 April 21 and …

Read more

With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change). Construction update: April 3 – April 21 …

Read more

The Calaveras County Water District is planning to interrupt water service for about 200 homes and 12 businesses in Arnold from 8 a.m. to noon Monday April 3. This water service outage is necessary to allow the District to perform a pipeline tie-in, which is part of the ongoing Reach 3A Transmission Pipeline Replacement Project. …

Read more