209-754-3543
customerservice@ccwd.org

Water Capital Improvements

Home » Water Capital Improvements

The Reach 3A Pipeline Replacement Project in Arnold is nearing completion. One 500-foot section of old pipeline remains between Oak Court and Pine Drive near the Black Bear Inn. During the final phase of construction, heavy equipment and construction activities will cause traffic delays and create noise in the area between 7 a.m. and 3:30 …

Read more

Construction Update   August 7-11 Crews will continue trenching and installation of new pipeline through Cedar Center and along Oak Court. Large equipment and construction activity will continue to create traffic delays in the area, and access to businesses and parking will be impacted by this work. August 13-18 Once new pipeline has been installed …

Read more

Construction Update July 24-28: Construction crews will complete the tie-in of a new section of pipeline into the main water distribution system on Blagen Road, which could cause minor traffic delays in the area on Monday July 24. On July 25, crews will begin trenching and installation of new pipeline near the cabinet shop at the …

Read more

Calaveras County Water District crews will begin replacing a large section of aging water pipeline on Ormes Court from its intersection with Siegle Street to the road’s western end this week, which will cause minor traffic delays in the area through the middle of August. This project is part of the District’s commitment to replace …

Read more

Construction Update July 17-21: Construction crews will be testing recently installed pipeline on Blagen Road and tying the new section of pipeline into the main system, which could cause minor traffic delays in the area. Additional work will take place near the District’s Sawmill Tank on the hill above White Pines Lake, but that work …

Read more

There will be a planned water outage from 9 a.m. to noon Friday June 23 in Arnold. This service disruption will impact all residential CCWD customers on Fir Street, Dunbar Road and Linebaugh Road. It will also impact Ebbetts Pass Gas, Chevron and Arnold Ace Home Center. Those with questions or concerns about this planned water …

Read more

Construction Schedule June 14-June 16: Crews will be trenching and installing 12-inch ductile iron piping along Dunbar Road. They will also tie in a pressure-reducing valve at the corner of Dunbar and Blagen Roads. Traffic control will be in effect during this work. Once the new section of piping is installed, they will begin testing. …

Read more

Construction Schedule May 30-June 2: Crews will be testing recently installed pipeline along Fir Street. This work may require minor traffic delays. June 5-9: Crews will be connecting a pressure-reducing valve to the water distribution system along Fir Street. They will also be installing ductile iron piping along Dunbar Road between its intersection with Fir …

Read more

Construction schedule: May 11 – June 9   May 22-25 – Crews will be installing ductile iron pipe on Fir Street heading northeast between Manuel Drive and Dunbar Road. Two pressure-reducing valves will be tied into the new system, and crews will pressurize and test the new section of pipeline. Residents should expect minor traffic delays …

Read more

Thousands of feet of aging water distribution pipeline will be replaced this summer as part of a construction project the Calaveras County Water District (CCWD) is launching in Rancho Calaveras. All construction work is being performed in-house by CCWD construction and distribution crews. The first phase of the project is on Harper Street, where crews …

Read more
Page 1 of 7 12345...Last page
Translate »